[Date Prev][Date Next][Thread Prev][Thread Next][Date Index ][Thread Index ]

YADANA GAS FIELD / MORE PROBLEMS AT



Subject: YADANA GAS FIELD / MORE PROBLEMS AT                 RATCHABURI  PLANT  

                                                            
                                        October 23, 1998 


                                    


      YADANA GAS FIELD / MORE PROBLEMS AT
                RATCHABURI PLANT 

 New delays damage
 all parties

 PTT hopes talks with Burmese can reach
 settlement

 Boonsong Kositchotethana

 New delays affecting the supply of Yadana gas from Burma to
 Thailand are damaging both countries and all investors involved.

 Burma faces delays in obtaining urgently-needed revenue; Thailand
 has to pay for gas it cannot process; investors in the Yadana field are
 paying mounting interest bills for no return; and contractors in Thailand
 face demands for compensation.

 Thailand is now unable to take commercial delivery of the offshore gas
 until April, almost nine months behind the original supply date and four
 months later than the previously rescheduled deadline.

 The longer delay stems from new difficulties experienced by Mitsui &
 Co of Japan and its American supplier, General Electric, in equipping
 the 1,800-megawatt Ratchaburi power station, according to Thai
 officials. The plant will be the only burner of Yadana gas for some
 years.

 The Petroleum Authority of Thailand (PTT), the gas buyer, is
 contracted to pay for supplies since last July, regardless of whether or
 not it takes delivery.

 PTT executives are due in Burma next month in a bid to persuade the
 Yadana development consortium, led by Total of France, to relax the
 conditions.

 Problems with the power station had already delayed the start of
 commercial operation of Burma's largest known offshore gas field to
 December this year.

 Senior officials of the Electricity Generating Authority of Thailand
 (Egat) said General Electric, which has a good track record in building
 power stations, appeared to have struck more problems with the
 delivery of initial units for the Ratchaburi plant from Mitsui.

 Mitsui had earlier told Egat that the first two 200-megawatt gas
 turbines at Ratchaburi would be ready for commissioning in
 November or December.

 "They (General Electric) seem to have problems with components
 manufactured by their production facilities," a senior Egat official
 noted.

 The delay in delivery of the two units would have a domino effect on
 the completion of the other generating units, Egat officials said.

 Egat has told Mitsui that the Japanese company will be subject to a
 penality fine of one billion baht for the delay - the maximum amount
 the authority can claim from Mitsui under its 10-billion-baht contract.

 The problems have more far-reaching implications for the PTT's
 ongoing negotiations with the Yadana developers to relax penalties for
 late purchase of gas.

 The PTT is citing force majeure - unforeseeable circumstances - for
 its failure to meet the contractual supply rate and dates in a bid to
 avoid heavy penalties under the 30-year take-or-pay deal.

 Since July 30, the PTT has been able to take delivery of only five
 million cubic feet per day of the 65 million initial rate stipulated in the
 Yadana contract.

 The initial flow was made possible only with the installation of a small
 25-megawatt turbine as a temporary burner. Egat moved the unit from
 Kamphaeng Phet.

 Under the contract, the PTT is committed to gradually raise its offtake
 of gas from Yadana, 240 kilometres south of Rangoon in the Gulf of
 Martaban, to a plateau level of 525 million cubic feet per day 15
 months after the scheduled production start-up date of last July 1.

 The PTT wants to pay only for the amount of gas actually taken, but is
 bound by contract to pay for the undelivered gas at year-end.

 But a legal expert said the PTT's citing of force majeure had come
 too late. Panas Tassaneyanont, former dean of Thammasat
 University's law faculty, said the step should have been taken while
 environmentalists were protesting against pipeline-laying in
 Kanchanaburi early this year. The government could then have
 ordered the PTT to stop the project, lifting liability from the agency.

 Pibhob Dhongchai, an adviser to the Kanchanaburi Conservation
 Group, a leading group of protesters against the laying of the Thai
 section of the Yadana line, said: "Had the PTT listened to the
 environmentalists, we would not have wasted a large amount of
 money and would have saved fertile forest." Thai environmentalists
 opposed the project on the grounds that it cut through rain forest and
 had displaced wildlife including elephants.

 The Burmese junta, through the state-owned Myanma Oil and Gas
 Enterprise, which has a 15% stake in the $1-billion Yadana project,
 has so far insisted that Thailand adhere to the original Yadana
 contract.

 "Burma is very unhappy with us because it had high expectations of
 steady, sizable revenue from the sales and planned to use the money
 to turn its economy around," said a senior PTT official involved in
 negotiations.

 John Imlee, president of Unocal Corp, a major shareholder in the
 Yadana development group, said the PTT's request for easier
 conditions needed to be addressed to the whole consortium. "I'm sure
 it will be worked out because we invested $1 billion together to have
 this gas," he said.

 Total of France has a 31.24% stake in Yadana, Unocal 28.26% and
 PTT Exploration and Production Plc of Thailand (part of PTT)
 25.5%. 

                                                       
                                                       Classifieds

                                                       Jobs
                                                       Property
                                                       Entertainment
                                                       Investment
                                                       Education
                                                       Travel
                                                       Sales

                                                       Learn English

                                                       Weekly 

                                                       Database
                                                       Horizons
                                                       NiteOwl
                                                       Student
                                                       Weekly
                                                       Real Time

                                                       Special

                                                       We Care
                                                       Street Art

                                                       Back Issues

                                                       Last Month
                                                       Archive

                                                       Company
                                                       Servcies
                                                       Subscriptions
                                                       Advertising

                                                       Annual Report
                  


 © Copyright The Post Publishing Public Co., Ltd. 1998
 Last Modified: Fri, Oct 23, 1998
 For comments and letters to the editor see : notes
 Comments to: Webmaster
 Advertising enquiries to Internet Marketing